曾大侠 发表于 2015-7-20 00:45:36

What are the site validation requirements for a radiated emission test site u...


Publication Number: 704992Rule Parts:Publication Date: 06/12/2015
Keyword: Test Site Validation Requirements above 1 GHZ

First Category:Test Sites and Accreditations
Second Category:General

Question: What are the site validation requirements for a radiated emission test site used to make measurements above 1 GHz?



Answer: The site validation requirements for radiated emissions compliance testing of unintentional (ANSI C63.4-2014) and intentional radiators (ANSI C63.10-2013) on an open area test site (OATS) (or alternative test site) are specified in Section 2.948(d). In general, test sites used for radiated emission measurements are required to comply with ANSI C63.4-2014, and validation of the test site shall be confirmed no less than once every three years.Test sites used to measure radiated emissions in the 30 MHz to 1 GHz range are required to comply with the site validation requirements in clause 5.4 of ANSI C63.4-2014.Test sites used for radiated emission measurements from 1 GHz to 40 GHz are required to meet the site validation requirements below:ANSI C63.4-2014 provides two options for test facilities used to make radiated emission measurements above 1 GHz: 1) the site validation criterion called out in CISPR 16-1-4:2010-04; or 2) a minimum area of the ground plane is covered with RF absorbing material as specified. ANSI C63.10-2013 requires the test site to conform to the site validation criteria called out in CISPR 16-1-4:2010-04. The FCC rules provide for a transition period for test sites to demonstrate compliance with the CISPR standard. During a three-year transition period, either option in ANSI C63.4-2014 may be used. However, at the end of the transition period, July 13, 2018, a test site used for radiated emission measurements for unintentional or intentional radiators is required to comply with CISPR 16-1-4:2010-04.Test laboratories are encouraged to start the transition to CISPR 16-1-4:2010-04 immediately so they have time to make any changes needed to their test sites to demonstrate compliance with the preceding requirements.

吴张利 发表于 2015-7-20 16:18:33

新的FCC实验室认可规则都出来了,从2015年7月13号后不再接受新的按2.948规则场地注册,以前注册的可以继续提交,直到2016年7月13日失效。

曾大侠 发表于 2015-8-16 22:59:39

吴张利 发表于 2015-7-20 16:18
新的FCC实验室认可规则都出来了,从2015年7月13号后不再接受新的按2.948规则场地注册,以前注册的可以继续 ...

是的,但是目前还是按照之前的做呀。另外,说不定在明年7月13日之前中国政府会与美国签署MRA协议呢。